Scheduled Maintenance - Hong Kong - Equinix HK1 - IP Core

Scheduled Maintenance Report for GSL

Completed

The scheduled maintenance has been completed.
Posted Oct 31, 2025 - 16:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 27, 2025 - 16:00 UTC

Scheduled

We will be performing scheduled maintenance starting Tuesday, 28 October (Local Time), to upgrade our routing infrastructure at Equinix HK1 to 400G-capable equipment.

During this window, some customers without protected services terminating in Equinix HK1 may experience a single brief service interruption as they are moved to this new equipment, lasting up to 30 seconds.

This maintenance will be performed outside of local peak hours to minimize any impact, nothing earlier than midnight, local time.
Posted Oct 22, 2025 - 03:19 UTC
This scheduled maintenance affected: IP Transit ((HK) Hong Kong), Backbone Network ((HK) Hong Kong), and Datacentres ((HK) Hong Kong - Equinix HK1).