Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 26, 2023 - 18:01 UTC
Scheduled
Our team will be performing an emergency firmware upgrade on several core network devices in Equinix TY8. This emergency maintenance is required to resolve a critical software bug we identified in several versions of Arista models we have deployed.
Due to the number of devices which need to be upgraded, we have allocated a 5 hour period. We have scheduled this maintenance to take place during the early hours of the morning to minimise the impact to customers. The expected downtime should not exceed 3 hours.
Start time: Sunday 27th August 3AM (UTC +9) End time: Sunday 27th August 8AM (UTC +9)
This upgrade is necessary to ensure the stability of our global network. We do apologise for any inconvenience caused.
Posted Aug 24, 2023 - 12:19 UTC
This scheduled maintenance affected: Datacentres ((JPN) Tokyo - Equinix TY8), IP Transit ((JP) Tokyo), and Backbone Network ((JP) Tokyo).